Commissioning Steps for a Vertical Gantry Machining Center


Published Time:

2023-04-18

Whether before leaving the factory or on-site during operation, a vertical gantry machining center must undergo careful adjustment to verify that the machining center is securely assembled and that all its transmission systems, control systems, and other software components function properly and reliably. Therefore, the machine tool’s commissioning procedure is of utmost importance. Let’s now take a look at the commissioning steps for a vertical machining center.

  Whether before leaving the factory or on-site during operation, a vertical gantry machining center must undergo careful adjustment to verify that the machining center is securely assembled and that all its transmission systems, control systems, and other software components function properly and reliably. Therefore, the machine tool’s commissioning procedure is of utmost importance. Let’s now take a look at the commissioning steps for a vertical machining center.

  Generally, the adjustment and trial operation positions for vertical machining centers should follow these steps:

  1. Lubricate each lubrication point of the vertical machining center according to the requirements specified in the instruction manual; fill the hydraulic oil filter element with gear oil that meets the standard specifications; and connect the pneumatic valves.

  2. Connect the power to the vertical gantry machining center. After each component has been individually powered up or after a single-power-up test for all components, check whether any alarms are triggered, manually inspect each component for potential issues, and verify that all protective devices are functioning properly. Ensure that all stages of the machine tool can be operated and controlled smoothly.

  3. Grouting: After the vertical machining center is initially operational, roughly adjust the machine tool’s geometric accuracy by aligning and adjusting key moving components and critical parts of the main unit. This includes the robotic arm, CNC tool, pallet changer, and component levelness. Once this work is completed, use fast-setting cement to fill the anchor bolts for the base and all associated accessories, ensuring that the holes reserved for each anchor bolt are completely filled and leveled.

  Four: Adjustment. Prepare various specialized testing tools, such as high-level levels, standard square rulers, and parallel square tubes.

  5. Precisely adjust the machine tool’s level to ensure that the geometric accuracy of the vertical machining center falls within the specified tolerance range. Use a slightly larger number of support pads, and after releasing the load, adjust the bed to achieve proper leveling. Verify the reliability of the bed after any modifications made through the inspection port.

  Six: To adjust the robotic arm using manual control methods, position it relative to the spindle bearing and use an adjusting mandrel. When assembling large-weight chucks, perform multiple automatic tool changes to the spindle bearing area to ensure accuracy and prevent collisions.

  7. Move the operating table of the vertical gantry machining center to the exchange position, adjust the alignment between the pallet station and the exchange worktable, ensuring that the operating table switches automatically in a stable posture. Then, install the operating table under its maximum load and perform multiple exchange cycles.

  Main applications of vertical gantry machining centers

  Mainly used in:

  1. In the gantry machining center, selecting lubricating oils and grease for circulating lubrication can also result in abnormally persistent hot spots.

  2. Like spindle bearings, the principle behind high-speed rolling bearings—characterized by relatively high clearance and enclosed installation—is as follows:

  Utilizing the fluidity of compressed gas within the pipeline, the grease is continuously and smoothly propelled along the inner wall of the pipe, mixing with oil vapor and being delivered to various lubrication points, including the spindle bearing in the machining center and other components such as ball screws. Dry compressed gas is supplied at a relatively stable working pressure (5–8 BAR), while the amount of grease supplied is precisely metered according to the differing lubrication requirements of the spindle bearing, ball screws, or other components.

  Therefore, each lubrication control circuit employs an independent miniature oil pump as the power source for the oil pipeline. After being pumped out, the oil first flows into the gas-mixing valve, where a stream of compressed gas blows the oil into tiny droplets, which adhere to the pipe wall and form a floating oil film. This floating oil film then flows along the pipe wall in a spiral direction. As it moves through the pipeline, the thickness of the floating oil film gradually decreases, yet it does not coalesce or solidify.


Related News

Message

If you have any questions, please contact us!

Submission